Integrated equipment turnkey installation for Shur-channel pumping station, Uzbekistan

General view of a pumping stationThe  transformer substation

    Project description
  • Under the project to support agricultural enterprises funded by the World Bank HYDROMASHSERVICE together with the Uzbek construction company carried out EPC for Shur-channel pump station situated in the Andijan region of Uzbekistan.
  • During the project implementation HYDROMASHSERVICE have built and equipped:
        - A pumping station;
        - Pressure pipeline with a diameter of 1200 mm;
        - High-voltage substation;
        - Electric power line.
  • Project was implemented over 11 months in 2006.
The station is the basis of Shur-channel that provides a guaranteed water supply for irrigating a number of districts in Bukhara region covering around 100 thousand hectares.