Complete pumping systems reconstruction for the 1st and 2nd levels of water supply system, Dushanbe, Tajikistan

The pumping station of one of the Dushanbe water intakes after reconstruction
The pumping station of one of the Dushanbe water intakes after reconstruction
Well washing
Well washing
    Project description
  • Dushanbe Water Supply Project included:
        - The five pumping stations of the 2nd level restoration;
        - The pumping stations electrical equipment replacement;
        - Installation of 25 new electric driven pumping units made by companies of Hydraulic Machines and
          Systems holding (now The HMS Group);
        - The city water supply system shift conception execution to groundwater sources (installation of 126
          deep-well pumps in artesian wells).
  • According to the contract completed in 2006 all pumps, valves, pipes, low voltage and high voltage electrical equipment were delivered and replaced.
As part Water Supply Project funded by World Bank loans, HYDROMASHSERVICE won tenders and signed contracts for all first and second lifts’ pumping stations complete reconstruction in Dushanbe, the capital of Tajikistan with 679,4 thousand inhabitants.
Well after reconstruction
Well after reconstruction
Borehole pump control station after renovation
Borehole pump control station after renovation